Projects
M6 Toll Road
M&E Construction Schedule
January 2001 - December 2003Architect
Ove Arup & WS Atkins JVServices
M&E Design & BuildMain Contractor
CAMBBASector
CommercialContract Value
£4 millionProject Images
M6 Toll Road
Toll1
M6 Toll Road
Ground Works
M6 Toll Road
from above
M6 Toll Road
M6 toll images
M6 Toll Road
M6 toll image
M6 Toll Road
Toll2
M6 Toll Road
Pumping station
M6 Toll Road
Toll booths
M6 Toll Road
empty toll road
M6 Toll Road
more traffic on m6 toll
Project Description
M&E works associated with the design, supply, installation and commissioning to a total of 8 sites along the full length of the toll road for all road tolling functions, toll plazas, pumping station, operations management centre, police station, snow plough shelter, salt barn and maintenance depot.
Scope of Works - Design and Project Management of:
Mechanical Services
All mechanical services to buildings and Shenstone Pumping Station including H&V installation, water services, sanitary installations, air conditioning, water treatment, fuel oil system, gas and air systems, centrifugal pumps and pressure testing
Electrical Services
All electrical services including power supplies, lightning protection, generators, UPS systems, emergency lighting, fire alarms, distribution transformers, switchgear, distribution boards, motor control centres, instrumentation and telemetry.